Tell me about a time you had a conflict at work.

During the SoS a team mentioned they were out of schedule due to my team innaction and lack of communication. I mentioned that i was unaware of such impediment but promptely offered to meet on the day after to discuss. Effectevely there was a cross team dependency that was not flagged in the quarterly planning and unfortunately was never raised until it became a blocker for the other team.

We worked out a new schedule and raised this to the team and product leads. With some push both teams were back on track before the issue evolved into something bigger.